September 28, 2019

Current Engineering Trends for the Execution of Capital Projects



It is increasingly common to hear from contractors and business specialists highlight the cost reduction achieved during the execution of capital projects by implementing, at least, one of the following approaches on project execution:

  • Engineering, Procurement and Construction execution based on Advanced Work Packaging (AWP).
  • Implementation of High-Value Engineering Centers (HVEC).
  • Application of 4D Planning and Scheduling (4D-P&S).
  • Application of Building Information Modeling (BIM).

A summary of the key characteristics of each approach is given below:

Advanced Work Packaging (AWP):

Engineering, Procurement and Construction execution based on the AWP means the sequential packetization of engineering deliverables so that the flow of this project information responds to the needs of the field construction, this in the form of predefined and sequentially programmed Construction Work Packages (CWP), that result in specific Installation Work Packages (IWP) of short execution periods.


In short, AWP is a construction-driven process that adopts the philosophy of “beginning with the end in mind.” The work packaging and constraint management process removes the guesswork from executing at the workface by tightly defining the scope of all work involved, and by ensuring that all things necessary for execution are in place.
Studies indicate that, under AWP scheme, capital projects have shown field productivity increases of up to 25% and reduction in total project costs by up to 10%.

Reference:
  • Construction Industry Institute. Knowledge Base. No. RT-272: “Enhanced Work Packaging: Design through WorkFace Execution” (Best Practice). Volume 3: Case studies and expert interviews as a supplement to aid effective implementation.

 High-Value Engineering Centers (HVEC):

Implementation of High-Value Engineering Centers means activating the remote participation of well-trained engineers working at engineering centers in developing countries such as Mexico, Indonesia, Venezuela, India, Africa, called High-Value Engineering Centers (HVEC), which allows obtaining highly qualified engineering teams at a low cost.



4D Planning and Scheduling (4D-P&S):

4D Planning and Scheduling means the linking of a 3D digital model with time or schedule-related information to create animated sequences that show a structure’s components being built up, including both permanent and temporary works. 


4D-P&S allows visualizing the project as sequential tasks planned in a model to create simulation, and also allows changing the tasks and dependencies to optimize and validate efficiently the sequence of activities. From this, you can evaluate whether the project is constructible as planned and also visualize the effects of the schedule on the model, and compare planned dates against actual dates. Costs can also be assigned to tasks to track the cost of a project throughout its schedule. Also, for instance, 4D-P&S visualization may allow scheduling a crane placement during the construction phase, improving its performance and thus avoinding any possible interference.

Building Information Modeling (BIM):

The BIM approach means that all project stakeholders (e.g., architects, engineers, contractors, owner, etc.) actively collaborate to create a complete virtual model of the project. It enables the virtual information of the model to be handed from the design team to the main contractor and subcontractors and then on to the owner/operator; so that each stakeholder adds specific data, comments or constrains to the single shared model. This greater collaboration between stakeholders takes full advantage of the potential cost reduction opportunities. Also, the BIM approach focuses on the concept that different components of a model “know” what they are supposed to do, so as the 3D model is altered, these types of components self-adjust in logical ways.


Studies indicate that the application of BIM brings reducing costs (up to 40% of unbudgeted change orders eliminated), improving the accuracy and speed of cost estimates (up to 80% reduction in time taken to generate cost estimate and cost estimation accuracy within 3%), increasing clashes/interferences prevention (up to 10% of the contract value is saved by detecting clashes), and shortening execution time (up to 7% reduction in project time) 

References:
  • German, P. 2012. Evaluation of training needs for Building Information Modeling (BIM). ProQuest, UMI Dissertation Publishing.
  • Gilligan, B.; Kunz, J. 2007. VDC Use in 2007: significant value, dramatic growth, and apparent business opportunity (CIFE technical reports) [online], [cited 11 December 2010].
  • Azhar, S.; Abid, N.; Mok, J.; Leung, B. 2008. Building information modeling (BIM): a new paradigm for visual interactive modeling and simulation for construction projects, in Proc. of the 1th International Conference on Construction in Developing Countries (ICCIDC–I), 4–5 August 2008, Karachi, Pakistan, 435–446.
  • Nisbet, N.; Dinesen, B. 2010. Constructing the business case: Building Information Modeling. British Standards Institution and BuildingSMART, UK.


But, all engineering approaches above-mentioned have their risks of deviation from the goals set.

Namely:

1.      Some potential risks of the AWP approach:
·      The AWP approach basically addresses Engineering Work Packages (EWP), Construction Work Packages (CWP), and Installation Work Packages (IWP). Therefore, Procurement Work Packages (PWP) must be well aligned with the respective CWP and IWP to avoid the lack of material or equipment in the field. Here, procurement manager monitoring is crucial.
·        Lack of clear AWP implementation strategy.
·        Lack of appropriate stakeholder support for the AWP.
·        Lack of identifying the key personnel required for supporting AWP.
·    Inadequate sizing of the Installation Work Packages (IWP) and also an inadequate estimate of the respective execution times.
·        Inadequate Installation Work Packages sequence.
·        Potential redundancy in the IWP contingencies.
·    Potential loss of the benefit of economies of scale in the acquisition of materials and equipment for the IWP.

2.      Some potential risks of the HVEC approach:
·        Inadequate communication between the Project Main Office (PMO) and the HVEC.
·        Lack of adequate supervision within the HVEC and by the PMO.
·      Transfer of incomplete work packages from the PMO to the HVEC, without an adequate definition of the split of work between both parties.
·        Lack of accountability within the HVEC.
·    Staff turnover in the HVEC with the consequent loss of personnel already trained and committed to the project.
·   Redundancy between PMO and HVEC in the use of expensive special software. That means a lack of integration between both parties about the efficient use of software licenses that could be shared.
·   Lack of integration between the IT groups of PMO and HVEC to achieve optimal communication between their servers.
·        Lack of an adequate execution plan shared between the PMO and the HVEC.
·        Inadequate planning of the HVEC activities within the PMO’s master plan.

3.      Some potential risks of the 4D Planning and Scheduling approach:
·        Project size could be a decisive factor for 4D-P&S applicability.
·       At the beginning of the project, the implementation of 4D-P&S may take longer time than other planning and programming approaches.
·        Planning and Scheduling with too many details that could reduce accuracy.
·        Increased exposure to the planning fallacy (for example, increased optimism bias, lack of proper unpacking of tasks, etc.)

4.      Some potential risk of the BIM approach:
·        At the beginning of the project, if there are no references to start modeling, BIM modeling could take longer than other CAD modeling and negatively impact productivity. But it should be noted that in the final phases of the project, BIM provides better performance for the extraction of 2D drawings, better model rendering, and expedite the exchange of model information with the client.
·        BIM upfront cost of modeling could be higher than CAD.
·        Project size could be a decisive factor for BIM applicability.


Therefore, it is recommended to evaluate each approach in light of its risks and to identify how to apply them and whether they are viable or not.

Next Steps Ahead:

  • Fully integration among AWP, HVEC, 4D-P&S, and BIM.
  • Tearing down the barriers, not written but widely accepted, as a result of fears of the Project Main Office management about the potential risks to which the HVEC would expose them during project execution.
Namely:
ü  No more than 30% of the engineering deliverables would be allocated to HVEC.
ü All key activities and deliverables must be kept within the execution of the Project Main Office.
  • Tearing down the paradigm that states that non-BIM 3D modeling approaches (e.g., CADWorx, Smartplant, PDS, etc.) should be used for the design of piping/mechanical and electrical assemblies for industrial plants, while BIM should be used exclusively in the design and construction of commercial and office buildings.

September 2, 2019

Monterrey. A thriving city that aims for more




Recently, I had the great opportunity to be in Monterrey, Mexico, providing project management services to a local company in the field of engineering projects.

My first impression of this city in northern Mexico was its obvious intention of modernity, captured by its magnificent new buildings under construction, in addition to those already built, which gives it a cutting edge profile among the main cities of Latin America. It is a city in rapid change and growth, which exudes prosperity and this, is perceived in everyday life. Added to this is the main symbol of this city, “El Cerro de la Silla” (Saddle Mountain), named for its similarity with a saddle on horseback, which gives the city its distinction.

After the pleasant visual impact received, there is the friendly, simple and respectful treatment of the “Regiomontano” (a term referring to the people from this city), very typical of the Mexican idiosyncrasy. To this must be added, already in the specific area of the execution of projects, that it can be verified the high skill and remarkable professional level of personnel located in this city. In the entire workgroup with which I shared my work, I observed great skills and technical capacity, cordiality, proactivity, pleasant openness, and transparency, commitment to the objectives set and high accountability in their actions. All these are key success factors for any company or entrepreneurship.

Also, it is perceived in the engineering projects environment, extended familiarization with the most recent approaches for the execution of projects, such as 3D Modeling, Advanced Work Packaging (AWP), 4D Planning & Scheduling, High-Value Engineering Centers (HVEC), and Building Information Modeling (BIM).

Everything described above, in addition to its very convenient proximity to the United States, gives Monterrey, a promising future for the intensive development of engineering projects. Not to mention the possible existence of tax incentives, which I could not validate, but which is very likely to exist. With which this city reinforces its position as a reference throughout the Americas as a fertile city for the development of all types of companies and especially those related to the area of engineering project execution.